Six moving parts, in priority order:
The architecture is informed by five convergent authoritative sources. It is an Editorial construction — published with its reasoning and its sources, not a black box. Sourced / Derived / Absent label individual figures and gate states; they do not apply to this design choice itself.
| Source | What it establishes |
|---|---|
| IRMA Standard for Responsible Mining (v1.0) | 4 principles / 26 chapters / 420+ requirements; per-pillar thresholds (a strong social score cannot offset a failing environmental score); a critical-requirement gate set, context-relevant (N/A where inapplicable); a grievance-cap rule (a dependent score cannot exceed the foundational score); unassessed = scored zero / "Not Assessed". The direct analogue for gates, cap, floors, and Absent. |
| SASB Metals & Mining | A defined material set of disclosure topics — structured as a set, not as weights (count per the current ISSB-stewarded standard; the architecture relies on the set/threshold structure, not a topic tally). |
| IFC CAO complaint data | In the CAO complaints record, land/resettlement ranks among the most-frequent complaint categories, with E&S assessment & management (PS1) among the most-raised. Establishes the Tier-1 ranking and the PS1 cap empirically. |
| Davis & Franks (2014, Harvard / UQ) | Davis & Franks identify community conflict as a dominant route from E&S risk to financial loss on world-class projects; the social / land / relationship dimension is the root, with environmental issues often the trigger. Establishes why social and land sit at Tier 1–2. |
| EY Top 10 Mining Risks | EY rank ESG / licence-to-operate as a top-tier, multi-year risk, with water, waste and nature elevated. Corroborates the tiering. |
Each gate renders one of: Met Not met N/A Absent. N/A where the trigger condition is absent; Absent (flagged, never imputed) where the trigger is present but the evidence is missing.
Lens toggle (§J): IFC Performance Standards is the default universal lens for private / blended-finance decisions. Switch to the World Bank Environmental & Social Framework for public-sector / sovereign decisions; the two are aligned, and the toggle re-bases which framework the gates, pillars and tiers reference. A segment-aware default (DFI / public → ESF; investor → IFC PS) is a fast-follow off the access-request role.
| Gate | Standard | Relevant when |
|---|---|---|
| G1 — ESIA + functioning ESMS | IFC PS1WB ESS1 | Always. Failure flags the whole score low-confidence (see the cap, §D). |
| G2 — Resettlement executed to standard | IFC PS5WB ESS5 | Where physical or economic displacement occurs. |
| G3 — FPIC process | IFC PS7WB ESS7 | Where Indigenous peoples are present. |
| G4 — Tailings / dam governance | GISTM | Where tailings storage facilities exist. |
| G5 — Critical-habitat assessment | IFC PS6WB ESS6 (via IBAT) | Where the asset is in or near critical habitat. |
The management-system confidence score caps every dependent component score: a component score cannot exceed the management-system score. This is the IRMA grievance-cap analogue, and the IFC CAO data shows PS1 management-system issues are pervasive. A weak or undemonstrated ESMS pulls the whole layer down rather than being averaged against a strong component elsewhere.
Three pillars are scored independently — Social, Environmental, Governance / Management — and each must clear its own floor. A failing pillar is not averaged away by a strong one. Each pillar score is Derived, carries a confidence tier, and draws only on Sourced or Derived inputs; a pillar with material Absent inputs renders its score Absent (flagged), not a mid-value.
| Tier | Components |
|---|---|
| Tier 1 — dominant | Land & resettlement (PS5ESS5) · Management-system integrity (PS1ESS1 — also the cap) |
| Tier 2 — major | Community health, safety & security (PS4ESS4) + vulnerable groups (AfDB OS7, §I) · Water, pollution & tailings (PS3ESS3 / GISTM) |
| Tier 3 — severity-gated | Biodiversity / critical habitat (PS6ESS6 ← IBAT, §G) · Indigenous / FPIC (PS7ESS7) |
| Tier 4 — lower | Labour (PS2ESS2) · Cultural heritage (PS8ESS8) |
Tier reflects how often a component binds, not its importance. A severity-gated component (Indigenous / FPIC, biodiversity / critical habitat) is dormant where it does not apply but dominant where it does: a failed FPIC gate flags the asset regardless of any other score, exactly as a failed Tier-1 gate would. Tier 3 is a statement about frequency of bind, never about the weight of Indigenous consent.
IBAT (Integrated Biodiversity Assessment Tool) is a recognised authoritative biodiversity-screening tool used at the investment / acquisition stage; its outputs are quantifiable and map to IFC PS6WB ESS6. IBAT feeds the biodiversity / critical-habitat component (Tier 3) and triggers the critical-habitat gate G5 where the asset is in or near critical habitat. It is an input to the layer, not a standalone widget. The IBAT → value mapping is documented; a missing IBAT input renders the component Absent.
Within the Tier-2 community component, Afrimintel surfaces AfDB Operational Safeguard 7 (vulnerable groups) as the explicit Africa-specific divergence — OS7 is broader than the IFC equivalent. It is framed as a divergence the score maps to, with a Sourced definition — not as an endorsement, and not as a partnership.
The IFC Performance StandardsWorld Bank Environmental & Social Framework lens is selectable at the top of §C. IFC PS is the default (the universal private / blended-finance reference and the larger audience); WB ESF is the public-sector / sovereign reference. The two are aligned. The toggle re-bases which framework underlies the gates, the pillars and the tiers. Both lenses are documented; a segment-aware default off the access-request role is a flagged fast-follow, not a blocker.
Components and gates render N/A where the trigger condition does not apply, and Absent (not-demonstrated / flagged) where the trigger applies but the evidence is missing. Absent is never imputed and never defaulted to a mid-value. This is the difference between "this asset has no tailings facility, so GISTM does not apply" (N/A) and "this asset has tailings, but its GISTM conformance is not on the record" (Absent — flagged).
Every gate result and every component score is shown with its basis and its state. No single number stands alone, and no black-box figure appears on any surface. The headline figure below (§L) is optional, secondary, and structurally subordinate to this decomposition.
For institutions that want a single number, an optional headline figure may sit on top of the decomposition. It is governed by the gates: a relevant gate failure caps or flags the headline so it can never mislead, and it never renders without the full decomposition beneath it. The aggregation weights are a Derived, configurable, secondary roll-up — not load-bearing; the gates, cap and floors do the work. The tier-band defaults are externalised to config/safeguards-rollup-weights.json and rendered as bands, never as fixed truth:
| Tier | Configurable band | State |
|---|---|---|
| Tier 1 (dominant) | 40–45% combined | Derived · config default |
| Tier 2 (major) | 30–35% | Derived · config default |
| Tier 3 (severity-gated) | 15–20% | Derived · config default |
| Tier 4 (lower) | 5–10% | Derived · config default |
Weights are configurable defaults, editorially confirmed at v0.1 (sign-off 19 Jun 2026) — non-blocking, because the roll-up is not the score.
Kabanga is a development-stage Tanzanian nickel project. This example shows the architecture doing both things it must: refusing to fabricate where the record is thin, and producing a composite once the safeguards record is sourced. Sourcing the DFC Initial Project Summary (2025), the Lifezone Feasibility Study Technical Report Summary (Jul 2025) and the SLR ESIA (2025) resolved the three gates that were previously Absent.
| Gate | State | Basis |
|---|---|---|
| G1 — ESIA + ESMS (PS1ESS1) | Met Sourced | ESIA + ESMP disclosed, IFC-PS aligned (Lifezone disclosures). "Functioning" confidence: moderate, pre-FID. |
| G2 — Resettlement (PS5ESS5) | Partial Sourced | Relevant (displacement occurs). RAP executed; cash compensation 97% complete (DFC / Lifezone disclosure, Dec 2025; 96% at the Jul 2025 FS), interest payments 95% (Dec 2025). Livelihood restoration — the PS5 core — co-design targeted early 2026, not yet demonstrated. Cash advanced; gate Partial, not Met. |
| G3 — FPIC (PS7ESS7) | N/A Sourced | Screened for Indigenous Peoples; none recognised in the area of influence. One Batwa family (Indigenous per Burundi) does not meet the PS7 diagnostic criteria in Tanzania, so PS7 is not triggered at this time (DFC Initial Project Summary, 2025). N/A — the Batwa are flagged as vulnerable under PS1 / PS5. |
| G4 — Tailings / GISTM | Met Sourced | Valley-type, downstream-constructed, fully lined TSF (120 ha, 50 Mt capacity, 72 m main embankment); subaqueous deposition for acid-generating tailings with a liner leakage-collection system; non-pyrrhotite tailings to underground paste backfill. The FS states relevant parts of ANCOLD, GISTM and the Tanzanian Dam Safety Guidelines have been met, with the design reviewed by an Independent Tailings Review Board (Lifezone FS TRS §1.8, Jul 2025). The FS classifies the TSF as an 'Extreme' consequence dam under GISTM, to be designed and operated to GISTM with independent third-party oversight (§1.14). Met by design — full operational GISTM conformance is pre-construction. |
| G5 — Biodiversity / critical habitat (PS6ESS6) | Partial Sourced | PS6 is among the applicable Performance Standards and biodiversity is a named major risk assessed in the IFC-PS-aligned ESIA + ESMP (DFC 2025; SLR 2025). The FS TRS §4.2 baseline characterises the site as a highly modified, long-cultivated agricultural landscape — predominantly devoid of large mammals, all plant communities human-impacted, common fauna limited to reptiles, birds and small rodents — consistent with IFC PS6 modified habitat. Partial — modified-habitat baseline now primary-sourced, but the formal critical-habitat trigger determination (FS TRS §17.3 / full ESIA) has not been read. |
ESMS documented (Sourced), confidence moderate pre-FID. The cap holds: no dependent component renders above this management-system confidence.
| Pillar | State | Basis |
|---|---|---|
| Social | Derived · clears floor (G2 Partial — reduced confidence) | Tier-1 land/resettlement Sourced (RAP cash 97%, Dec 2025); broader community evidence partial — pillar floor cleared, confidence capped by §D. |
| Environmental | Derived · clears floor (design-stage confidence) | G4 (tailings — lined downstream TSF, relevant GISTM parts met, ITRB-reviewed; Sourced) and G5 (PS6 biodiversity assessed, §4.2 modified-habitat baseline; Sourced) inputs now support the floor; it clears at design-stage confidence. Full operational GISTM conformance and the formal critical-habitat determination firm up at construction / FID. |
| Governance / Management | Derived · clears floor | ESMS + RAP governance Sourced; confidence moderate. |
RENDERS — moderate-confidence composite All five gates resolve — G1 Met · G2 Partial · G3 N/A · G4 Met (design) · G5 Partial — so none is Absent or Not-met and the layer no longer flags. Because the inputs are Sourced (not Absent), all three pillar floors are assessable; the PS1 cap holds the composite at moderate confidence pre-FID. The optional numeric headline (§L) still renders no single number here — the tier weights are now editorially confirmed (v0.1), but a figure stays withheld because the per-component confidence inputs remain bounded by the unread G5 critical-habitat determination (FS TRS §17.3); the gated assessment outputs the moderate-confidence composite, not a false-precision number. Confidence limiters: G2 livelihood restoration (early 2026); G4 full operational GISTM conformance (design met + ITRB-reviewed, pre-construction); G5 formal critical-habitat determination (FS TRS §17.3, not yet read; §4.2 baseline indicates modified habitat).
Earlier this surface showed three Absent gates and flagged — correctly, because the safeguards record had not been sourced. Sourcing the DFC Initial Project Summary (2025), the Lifezone FS Technical Report Summary (§1.8, Jul 2025) and the SLR ESIA (2025) moved all three off Absent — G3 to N/A (PS7 not triggered), G4 to Met by design (lined downstream TSF, subaqueous deposition; relevant parts of ANCOLD / GISTM met, ITRB-reviewed) and G5 to Partial (PS6 biodiversity assessed; critical-habitat determination still in the full ESIA) — so the composite renders at moderate confidence instead of flagging. The architecture is demonstrated doing both: flagging on absent evidence, scoring on sourced evidence — on one asset.
Read this the right way. Kabanga is not "low-scoring." It is partially demonstrated: strong and Sourced on the Tier-1 land/resettlement gate, undemonstrated on tailings governance and critical-habitat screening. The gate-and-floors architecture surfaces exactly that, and declines to average it into a misleadingly clean number. Filling G4/G5 (a GISTM conformance source and an IBAT screen) is what moves this from flagged to scored — through audit-logged updates, not estimation.
Loulo-Gounkoto is an operating top-10 gold complex in western Mali (Barrick 80% / State of Mali 20%), in continuous production since 2005. Where Kabanga showed the architecture producing a composite once a thin record is sourced, Loulo shows the architecture's other essential behaviour: flagging an established, well-run asset where one relevant gate is currently broken — and refusing to average that away. The G4 finding here also corrected a prior platform overclaim (a group-level "GISTM disclosed for all facilities" statement that did not hold for this specific TSF).
| Gate | State | Basis |
|---|---|---|
| G1 — ESIA + ESMS (PS1ESS1) | Met Sourced-secondary | Functioning ESMS: ESMP compliant with Malian regulation on a DNACPN five-year audit cycle, ISO 14001:2015 certification retained through annual audits, multiple active environmental permits including recent expansion ESIAs (Yalea open pit Dec 2022; Gara West Oct 2021). Confidence caveat: the 2025 provisional-administration period (Jan–Nov 2025, Barrick lost site access) interrupts continuity assurance — resolved by the Nov 2025 settlement reopening the complex under Barrick. |
| G2 — Resettlement (PS5ESS5) | Absent flagged | Relevance probable (open-pit expansions on an established complex along the Falémé), but no Resettlement Action Plan or displacement record located on the public record. Flagged — not imputed, not assumed N/A. Resolving it needs a primary RAP / livelihood-restoration source. |
| G3 — FPIC (PS7ESS7) | N/A Sourced | Screened for Indigenous Peoples; the Kayes-region populations do not meet the IFC PS7 diagnostic criteria, so PS7 is not triggered. N/A. (AfDB OS7 "Vulnerable Groups" is broader and remains live as context, §H.) |
| G4 — Tailings / GISTM | Absent Sourced | The material flag. Barrick's August 2025 GISTM disclosure expressly excluded the Loulo-Gounkoto TSF: under provisional administration Barrick had lost site access and could not verify conformance at this facility (mining trade press reporting Barrick's own disclosure). Barrick co-developed the GISTM and conforms at all 17 of its other Very-High/Extreme facilities — but Loulo-Gounkoto's facility-specific conformance is not on the record. The complex reopened under Barrick in Nov 2025; re-disclosure is pending the next annual cycle. A relevant gate not met-on-record flags the asset. |
| G5 — Biodiversity / critical habitat (PS6ESS6) | Absent flagged | No IBAT critical-habitat determination on the public record. The transboundary Falémé River aquatic context is a flagged consideration (authorised withdrawal 3,024,000 m³/yr from the Senegal River system, shared with Senegal); Birimian belt, not in an IUCN A-category protected area per prior Inferred analysis. Resolving it needs an IBAT screen. |
ESMS documented (ISO 14001:2015; Sourced-secondary), confidence moderate with the 2025-continuity caveat. The cap holds; it does not lift the asset off the G4 flag below.
| Pillar | State | Basis |
|---|---|---|
| Social | Derived · clears floor (reduced confidence) | ~97% Malian workforce, $1bn+/yr economic contribution, 74% local procurement (Sourced-secondary). Confidence capped: the G2 resettlement record is Absent. |
| Environmental | FLAGGED — does not clear | G4 (tailings GISTM conformance Absent / undisclosed for this facility) is a relevant gate not met-on-record; under the architecture this flags the asset regardless of any component score. G5 critical-habitat is also undetermined. The Environmental pillar does not clear. |
| Governance / Management | Derived · clears floor (flagged, resolved) | ESMS governance Sourced-secondary. Governance volatility — the 2024–25 dispute, provisional administration (Jan–Nov 2025), and the Nov 2025 settlement (~$430M; ICSID claims withdrawn; reopened under Barrick) — is recent but resolved. |
FLAGS — no composite renders A relevant gate is Absent on the record (G4 tailings conformance), so the layer flags and the optional numeric headline (§L) does not render — exactly as designed. This is not a low score; it is a withheld one. Loulo is a functioning, audited, top-10 producer whose tailings-conformance evidence is currently off the public record for a documented reason (the 2025 provisional administration severed Barrick's access). The architecture refuses to average a strong social/governance profile over a broken environmental gate into a misleadingly clean number.
Two assets now demonstrate both behaviours the architecture must show: Kabanga scoring to a moderate-confidence composite once the record was sourced, and Loulo flagging where a relevant gate is broken. What moves Loulo from flagged to scored: Barrick's next GISTM re-disclosure for the Loulo-Gounkoto TSF post-reopening (G4), an IBAT critical-habitat screen (G5), and a resettlement / livelihood-restoration source (G2) — through audit-logged updates, not estimation.
Why this matters to a financier. A DFI or lender screening Loulo learns the one thing that changes the decision: its tailings GISTM conformance is currently unverifiable on the public record, access having only just been restored (Nov 2025). That is a material safeguards flag a clean aggregate score would have buried. The architecture surfaces it, names the reason, and states exactly what evidence closes it.
Beyond the two worked assets. The same gate framework is applied at screening depth across a cohort of development-stage African critical-minerals juniors (Ewoyaa, Kasiya, Lindi Jumbo, with Kabanga) for the DFI / EBRD junior-mining lens: development-stage safeguards screening →