Guidance & claims register v0.1

African mining runs on forward claims — production guidance, study economics, first-pour dates, and corporate and deal milestones. This register records them as made, with claimant, date, and source, and scores each against the verified outcome when it can be Sourced. Until then the outcome is Absent — displayed, never guessed. No claim is endorsed by appearing here; the register is the scorecard, and it only grows more valuable as reality arrives. Feed: /api/v1/claims.json. Every open row is sourced to the claimant’s own primary release or filing — operator press release, DFS/NI 43-101, or exchange filing — not to secondary trade press.

Named in a row? You have a standing right of reply, published alongside it. Spotted a wrong figure on an intelligence-grade asset? See the error bounty. Near-term resolutions are pre-announced on the Verified Drop: outcomes publish either way.

AssetClaimantClaimClaim dateSourceStatusOutcome
koneMontage GoldFirst gold pour late Q4 2026 (oxide circuit)2026-01-19Montage Gold Corp. press release "…first gold pour expected in late Q4-2026", 19 Jan 2026 (GLOBE NEWSWIRE / montagegold.com); reconfirmed 15 Jun 2026openAbsent
kamoa-kakulaIvanhoe Mines2026 copper-anode production guidance 290,000–330,000 t2026-03-31Ivanhoe Mines press release + NI 43-101 Kamoa-Kakula MRE (eff. 31 Dec 2025), 31 Mar 2026 (ivanhoemines.com / SEDAR+)open — revised again to 290,000–310,000 t on 29 Jul 2026 (Ivanhoe Q2 2026 financial results); supersedes the withdrawn 380,000–420,000 t of 3 Dec 2025. Full trail on the record: 380–420 (Dec 2025) → 290–330 (Mar 2026) → 290–310 (Jul 2026). Scoreable against actuals at 2026 year-end.Absent
qala-shallowsWest Wits MiningFirst gold pour targeted March 2026as guided by West Wits Mining (ASX filings)West Wits Mining ASX development updates (primary filings); first-pour timing per company guidanceopen — outcome back-check queuedAbsent
assafouEndeavour MiningDFS upfront capital US$1,061m; NPV(5%) $2.1bn, 28% IRR at $2,500/oz; FID targeted end-20262026-04-23Endeavour Mining plc Assafou DFS results, 23 Apr 2026 (endeavourmining.com / GLOBE NEWSWIRE); NI 43-101 technical report to followopen — FID scoreable end-2026Absent
goulaminaGanfeng LithiumPhase 2 expansion to 1,000,000 t/yr spodumene concentrate2024-12-16Ganfeng Lithium statement, 16 Dec 2024 (via S&P Global 17 Dec 2024) + Leo Lithium DFSopenAbsent
simandouConsortium (per project reporting)Commissioning targeted 30 June 20262026-03Reported via Mining Review Mar 2026withdrawn — capture error, corrected on the recordWithdrawn 2026-07-05: the 30-Jun-2026 commissioning line was misattributed in capture. Simandou's commissioning ceremony took place mid-November 2025 at Morebaya (first shipment departing; SCMP 15 Nov 2025); the first cargo (200,000 t) arrived in China January 2026 (S&P Global, 19 Jan 2026); SimFer reported first commercial sales April 2026 (industry reporting). The register corrects itself in public — that is the product.
simandouCERA analysts (via S&P Global)Simandou exports ~15 million t in 20262026-01S&P Global Commodity Insights, 19 Jan 2026open — scoreable at 2026 year-endAbsent
allied-goldAllied Gold / Zijin GoldZijin Gold to complete 100% acquisition of Allied Gold by the outside date2026-05-29Allied Gold Corp Form 6-K / GLOBE NEWSWIRE, 29 May 2026 (ICA, ECOWAS & COMESA cleared; outside date 29 Jul 2026)scored — NOT MET; terminated 29 Jul 2026Zijin merger agreement terminated 29 Jul 2026; replaced by a ~US$295m Zijin strategic investment (Allied Gold Q2 2026, 5 Aug 2026).
allied-goldAllied Gold / Zijin GoldZijin strategic investment (12.8m shares @ C$32.55, ~9.2%) completes on or around 10 Aug 20262026-07-29Allied Gold release, 29 Jul 2026; resolution 10 Aug 2026scored — METClosed 10 Aug 2026; 12,800,000 shares at C$32.55 for C$416,640,000 gross; Zijin ~9.2%.
allied-goldAllied Gold / Zijin GoldZijin subscription shares hold period ends 11 Dec 20262026-08-10Allied Gold release, 10 Aug 2026open — scoreable at 11 Dec 2026Absent
kipushiIvanhoe Mines2026 zinc-in-concentrate production guidance 240,000–290,000 t2026-01-15Ivanhoe Mines press release "2025 Production Results, 2026 Production Guidance", 15 Jan 2026 (ivanhoemines.com / Newsfile Corp.)open — scoreable at 2026 full-year results (Q1 2027)Absent
kansanshiFirst Quantum Minerals2026 copper production guidance 175,000–205,000 t (Zambia); marginally below prior guidance for increased ore hardness2026-01-15First Quantum Minerals press release "2025 Preliminary Production and 2026–2028 Guidance", 15 Jan 2026 (first-quantum.com / SEDAR+)open — scoreable at 2026 full-year results (Jan 2027)Absent
sentinelFirst Quantum Minerals2026 copper production guidance 190,000–220,000 t (Zambia); reduced for Ball Mill 2 maintenance after 2025 fatigue failures2026-01-15First Quantum Minerals press release "2025 Preliminary Production and 2026–2028 Guidance", 15 Jan 2026 (first-quantum.com / SEDAR+)open — scoreable at 2026 full-year results (Jan 2027)Absent
kurmukAllied GoldKurmuk (Ethiopia) commissioning expected later in 20262026-06-10Allied Gold Corp Form 6-K filings (SEC); commissioning “later in 2026” per issuer filings (incl. 10 Jun 2026)open — scoreable on first gold / commissioning at Kurmuk (2026)Absent
nyanzagaPerseus MiningFirst gold pour targeted January 2027 (US$523m build; 80% Perseus / 20% Tanzania)2026-02-20Perseus Mining H1 FY26 results, 20 Feb 2026 (GLOBE NEWSWIRE / perseusmining.com); reiterated in the Dec-2025 quarterly, 29 Jan 2026open — scoreable at first pour, targeted Jan 2027Absent
perseus-portfolioPerseus MiningFY2026 group production guidance 400,000–440,000 oz at AISC US$1,600–1,760/oz (all-African: Edikan, Yaouré, Sissingué)2026-02-20Perseus Mining H1 FY26 results, 20 Feb 2026 (GLOBE NEWSWIRE); FY26 to 30 Jun 2026open — SCORING WINDOW ELAPSED: the FY26 Q4 report (period ended 30 Jun 2026) is the settling document and is now due; outcome pending a read of Perseus's own primary release. Flagged 18 Aug 2026 rather than left silent.Absent
waf-portfolioWest African Resources2026 group gold production guidance 430,000–490,000 oz at AISC below US$1,900/oz (Burkina Faso: Kiaka first full year, Sanbrado)2026-03-30West African Resources 2026 production guidance (ASX: WAF, Mar 2026), reaffirmed in the Q1-2026 quarterly reportopen — scoreable at 2026 full-year results (early 2027)Absent
endeavour-portfolioEndeavour MiningFY2026 group production guidance 1,090,000–1,265,000 oz at AISC US$1,600–1,800/oz (all-West-African: Houndé, Mana, Ity, Lafigué, Sabodala-Massawa)2026-03-05Endeavour Mining plc FY-2025 results, 5 Mar 2026 (LSE/TSX: EDV; endeavourmining.com); guidance issued 29 Jan 2026open — scoreable at FY2026 year-endAbsent
kabangaLifezone MetalsFinal Investment Decision targeted mid-2026, with financial close of the multi-source funding package2025-12-11Lifezone Metals press release, 11 Dec 2025 (BUSINESS WIRE / NYSE: LZM); builds on the 18 Jul 2025 feasibility studyclosed — NOT MET; restated to Q1 2027FID did not occur by mid-2026; claimant restated the target to Q1 2027 (Lifezone H1 2026, Form 6-K, 29 Jul 2026).
kabangaLifezone MetalsFinal Investment Decision expected Q1 20272026-07-29Lifezone Metals H1 2026 Interim Financial Results, Form 6-K, 29 Jul 2026 (SEC EDGAR; NYSE: LZM)open — scoreable at FID / financial close, targeted Q1 2027Absent
tulu-kapiKEFI Gold and CopperFirst gold production targeted from 2028; two-year build commenced Feb 2026 (US$340m financing closed); ~140koz/yr open pit over 7 years2026-02-18KEFI Gold and Copper (AIM: KEFI) Tulu Kapi groundbreaking + financing updates, Feb 2026 (kefi-goldandcopper.com); 2025 Business Planopen — scoreable at first production, targeted 2028 (previously guided 2026, then 2027)Absent
doropoResolute MiningFID taken March 2026 on Doropo (Côte d'Ivoire); 204,000 oz/yr over first 5 years; initial capex US$516m; 13-year mine life2026-03Resolute Mining (ASX/LSE: RSG) Doropo final investment decision, March 2026open — scoreable at first production (per Resolute's build schedule)Absent
diamba-sudFortuna MiningDiamba Sud (Senegal) FS 29 Jun 2026: first gold targeted Q2 2028; NPV5% ~US$1.0bn, IRR 60% at US$3,500/oz, initial capex US$397.5m; 158koz/yr first 4 years; FID pending mining permit2026-06-29Fortuna Mining Corp (NYSE: FSM / TSX: FVI) Diamba Sud feasibility study, 29 Jun 2026 (fortunamining.com / GLOBE NEWSWIRE)open — scoreable at FID (permit-gated) and first gold, targeted Q2 2028Absent
ewoyaaAtlantic LithiumEwoyaa (Ghana) mining lease ratified by Parliament Mar 2026 — Ghana's first lithium lease; advancing toward FID for spodumene production, ~US$185m financing outstanding (Elevra earn-in / 50% offtake)2026-03-20Atlantic Lithium Ltd RNS "Parliamentary Ratification of Ewoyaa Mining Lease", 20 Mar 2026 (AIM: ALL / ASX: A11 / GSE: ALLGH)open — scoreable at FID / financing close (no company date stated)Absent
bankanPredictive DiscoveryBankan (Guinea) DFS: construction targeted Q2 2026, commercial production Q2 2028; ~250,000 oz/yr over 12-year life; capex US$463m, AISC US$1,057/oz; FID pending exploitation permit2026-04-14Predictive Discovery (ASX: PDI) Bankan project page + DFS (predictivediscovery.com); exploitation permit in final reviewopen — SCORING WINDOW ELAPSED for construction start (Q2 2026, now closed); first production Q2 2028 remains future. Outcome pending Predictive Discovery's own release confirming construction start or continued permit gating. Flagged 18 Aug 2026.Absent
kayelekeraLotus ResourcesKayelekera (Malawi) uranium: steady-state 200,000 lb/month (2.4M lb/yr U3O8) targeted Q2 2026 (originally Q1 2026); restarted Aug 2025; production paused mid-2026 on acid-supply / furnace issues2026-04-11Lotus Resources (ASX: LOT) production updates, Q1–Q2 2026; steady-state guidance per MD Greg Bittaropen — SCORING WINDOW ELAPSED: Q2 2026 closed with production paused and an extended ASX voluntary suspension reported. Outcome blocked on primary — the register bar requires Lotus's own ASX releases, not trade press. Flagged 18 Aug 2026.Absent

The platform scores itself

Same rule, applied inward: Afrimintel's own forward statements, on the same scorecard.

ClaimantClaimDateSourceStatus
AfrimintelThe intelligence-grade verification queue converts via desktop back-checks; each promotion is published with source and state2026-07-05Audit log v2.137.0–v2.137.3in progress — 0 of 12 converted as at 18 Aug 2026; no conversions in the six weeks since 5 Jul. Stated rather than left to read as current.
AfrimintelKamoa-Kakula intelligence-grade record self-audit (due 7 Aug 2026)2026-07Published audit cadencescored 2026-08-16 — record holds (published late); no correction
AfrimintelLobito-corridor record self-audit (due 25 Sep 2026)2026-07Published audit cadenceopen
The register-cycle digest.

Each scored cycle by email — what we corrected, which rows resolved, and what resolves next. Sourced, dated, no spam.

Afrimintel · claims register v0.1 · composed at build v2.137.66 · every figure Sourced, Derived, or Absent — no fourth state.